2013: Installed over 2 miles of 6″ and 8″ poly pipe to connect paving plants operated by Continental Paving in New Hampshire to Natural Gas for Liberty Utilities.

2013: Installed 22 miles of natural gas main and transmission line to connect the City of Augusta, ME.

2013: Installed 1,530′ of 3″ natural gas line in Poland Spring, ME for Snowman Construction.

2012: Installed 850’ of 6” Natural Gas line under wet land at the new Maine General Hospital in Augusta, ME  for Maine Natural Gas.

2011: Installed 22,150’ of 6” and 8” natural gas main from Brunswick, ME to Bath Iron Works in Bath, ME.

2010: Installed over 8,000′ of gas line to connect Pownal and Freeport, ME to Natural Gas.

2008: Installed over 70,000’ of gas line in the Brunswick, Topsham, Windham and Gorham, Maine area for Maine Natural Gas.

2007: Installed 4,500’ of 4” gas main throughout Bowdoin College in Brunswick, ME.

2004: Installed 6,200’ of 6” Gas main as part of a gas upgrade for NEUCO of Everett, Ma in Riverside, NH.